Duct takeoff by system
Section colours
Pick a colour for each section. The choice applies to every system sheet and the Summary sheet.
Rectangular supports
Pick a hanger type. Sizes are picked by the duct's largest side. Bar / channel / strap is rounded up to supplier standard lengths.
Trapeze (angle bar or strut channel): 1 cross member (largest side + 2 × allowance) · 2 threaded rods · 2 expansion bolts · 4 nuts · 4 washers. Strap hanger: 1 strap (duct perimeter + 2 × allowance) · 2 expansion bolts. Wall bracket: 1 angle (largest side + 2 × allowance) · 2 expansion bolts. Bracket + wrap-around strap (near walls / columns): the bracket above + 1 strap around the duct + 2 bolt & nut sets. Supports per duct = ROUNDUP(length ÷ spacing). Rod settings only apply to trapeze types.
Round duct supports
Hanger + fasteners. Sizes are picked by the duct diameter. Band is rounded up to supplier standard lengths.
Band + rod type: each support = 1 band loop (π × diameter + 2 × allowance) · 2 threaded rods · 2 expansion bolts · 4 nuts · 4 washers. Angle bar trapeze: 1 angle bar (diameter + 2 × allowance) · 2 rods · 2 expansion bolts · 4 nuts · 4 washers. Wall bracket + wrap-around band: 1 angle bar + 1 band loop · 2 expansion bolts · 2 bolt & nut sets. Strap / wire type: each support = 1 loop + 2 fasteners. Supports per duct = ROUNDUP(length ÷ spacing).
Pipes are counted by length only: no gauge, sheets or tons. Sizes are read as nominal DN (inch sizes such as 2-1/2" are converted to DN65).
Pipe supports
Spacing and rod size are picked by the pipe DN and the material class. SMACNA’s hanger tables cover ducts; for piping SMACNA refers to MSS SP-58 / SP-69 hanger spacing (water service), which this preset follows. Edit any value.
Supports per size = ROUNDUP(length ÷ spacing). Rod-hung types (clevis, split ring, band, spring, roller): 1 hanger · 1 threaded rod · 1 expansion bolt · 2 nuts · 2 washers per support. Trapeze: supports ÷ pipes per trapeze = trapezes (use 2 for a supply + return pair); each has 1 strut channel of the trapeze length · 2 rods · 2 bolts · 4 nuts · 4 washers, plus 1 pipe clamp per pipe support. Wall bracket: 1 angle · 1 U-bolt · 2 nuts · 2 expansion bolts. J-hanger, strap and saddle: 1 item · 2 fasteners. Insulated systems add 1 shield / saddle per support. Use band hangers or saddles on insulated lines, spring hangers for vibration or vertical movement, roller hangers for axial expansion, and J-hangers / straps only on small light pipes. Riser clamps (vertical pipe) are not included because the schedule has no vertical / horizontal split; count them per floor. Plastic spacing is a typical value for PVC / PPR at chilled water temperature; check the manufacturer’s table.